Hut 8 Cash Flow and Debt Serviceability

17 October 2026Issuer noteDownload

Theseus credit protection research | 17 October 2026

USD millions unless stated otherwise | Fiscal year ends 31 December

Executive assessment

Hut 8 is the issuer in the nine-name book whose debt is least likely to default on a date, and the one where a credit short has no object. Its 7.5 billion dollars of debt is two series of fully amortizing, investment-grade project notes with no bullet, no parent guarantee and no tenant guarantee, secured on campuses leased to a Google-backstopped tenant and to an unnamed hyperscaler the market believes is rated AA minus or better. The parent carries no general-recourse term debt after the Coatue convertible converted in May 2026. There is no parent bond, no convertible and no CDS. The thesis, to the extent it applies, is an equity thesis about construction delivery and the financing of a third campus phase, and the equity short the desk already holds is its only expression.

The vulnerable link is not the debt service. It is the equity cushion: River Bend was financed at about 95% loan-to-cost with 184 million dollars of prior equity returned to the parent at closing, so a cost overrun or delay at either campus is funded from a parent that held 234 million of unrestricted cash at June 30, roughly 360 million of unencumbered bitcoin at current prices, and a new 1.07 billion revolver whose minimum-liquidity covenant begins to bind in March 2027. Beacon Point Phase 2, 352 MW and about 4.5 billion of construction, is contracted but unfinanced, and its equity layer has to come from the same pool. [Confidence: High on the structure, Medium on the overrun exposure]

The modeled outcome

In a delivery scenario, both campuses on schedule and Phase 2 equity of about 450 million, parent cash before the revolver, ATM or bitcoin sales turns negative in June 2027 at 146 and troughs at 316 in September 2027 before River Bend distributions begin. In a delayed-delivery scenario with 550 million of overruns and 700 million of Phase 2 equity, parent cash is negative by March 2027 and the cumulative requirement reaches 1,256 by June 2028. In a severe scenario with 1,100 million of overruns and 900 million of Phase 2 equity, the requirement is 2,086 by June 2028. The first two are inside the parent's identified remedies; the third is not without equity. These are analyst scenarios on undisclosed budgets, not forecasts of a missed payment. [Confidence: Medium]

Why this is not a short on AI, and barely a short on credit

A fall in AI demand does not reach Hut 8's creditors. The River Bend lease is backstopped by Google for rent and pass-through obligations for the full 15-year base term; the Beacon Point leases are triple-net, take-or-pay obligations of a high-investment-grade company. The notes were sized to those cash flows at about 1.3 times debt-service coverage after full amortization. Disappointment reaches the equity through three channels only: a construction overrun or delay that the 5% equity cushion cannot absorb, a Phase 2 financing that prices worse than Phase 1 or does not come, and a bitcoin price fall that impairs the parent's own liquidity and American Bitcoin's. None of those is a CDS event anywhere in the structure. [Confidence: High]

Market conclusion

No Hut 8 CDS exists and none can, since there is no deliverable obligation at the parent. The River Bend notes carried a fair value of 3.30 billion and the Beacon Point notes 4.30 billion at June 30, both above par. A short of either is a short of Google or of an AA-rated hyperscaler with a 16-year amortizing structure behind it. No dealer was contacted. The only tradeable expression of a negative view is the common stock at 67.75 on October 16, with the American Bitcoin stake as a second, more bitcoin-sensitive instrument.

Historical cash flow and the funding bridge

Six months to June 30, 2026, as reported

Cash flow item [1]H1 2026Note
Net cash used in operating activities(32.8)Net loss of 430.3 offset by 325.1 of non-cash items, chiefly digital asset losses
Purchases of property and equipment(616.2)River Bend and Beacon Point construction, substations
Bitcoin purchased(65.3)American Bitcoin's accumulation
Net proceeds from sale of the Far North JV64.8310 MW Ontario gas plants sold to TransAlta, February 2026
Net cash used in investing activities(635.1)
Proceeds from loans and notes payable7,700.03,250 River Bend, 4,250 Beacon Point, 200 FalconX
Repayments of loans and notes payable(217.7)Coinbase facility 200 and TZRC note 17.7
Debt issuance costs paid(84.5)
Hut 8 ATM, net120.12.1 million shares
American Bitcoin ATM, net144.1Consolidated but not the parent's cash
Net cash provided by financing activities7,640.7
Cash and restricted cash, opening to closing48.6 to 7,020.7Of which 6,787.1 restricted in project accounts

Operating cash flow is a mining company's: Q2 revenue of 74.9 was 72.5 of compute, almost all American Bitcoin's self-mining, with 1.2 of power and 1.3 of colocation revenue. Adjusted EBITDA under the new definition that strips the bitcoin mark was 10.4 for the quarter; including the mark it was negative 94.6. No hosting revenue exists yet. Interest cost incurred in Q2 was 56.8, of which 5.7 was capitalized, and that quarter held the River Bend notes for two months and the Beacon Point notes for three weeks; the run rate on both series is about 462 a year, paid from the interest and debt service reserves inside the project accounts until rent commences. [1, 2]

June 30 cash and bitcoin by holder

Balance [1, 2]AmountInterpretation
Unrestricted cash233.6The parent's and American Bitcoin's together; the company attributes 497.2 of cash and bitcoin to American Bitcoin
Restricted cash and equivalents6,787.1Net note proceeds in River Bend and Beacon Point construction and debt service reserve accounts, plus letter of credit collateral; not available to the parent
Bitcoin, total17,316 BTC, 1,036.5Implied price about 59,900 at June 30; about 80,000 in mid-October
Held in custody, unencumbered9,376 BTC, 561.3Split between Hut 8 (about 4,465 BTC) and American Bitcoin (about 4,912 BTC)
Pledged to Bitmain for miners3,090 BTC, 184.9American Bitcoin; a 371.7 miner purchase liability stands against it
Pledged as collateral to FalconXabout 4,850 BTC, 290.3Secures the 200 term loan; 143% initial ratio, margin call at 130%, liquidation at 105%
Hut 8 parent liquidity, own accountabout 234 cash plus about 267 of free bitcoin at June, about 360 at 80,000Before the Two Prime 200 and the September revolver

The company's statement of 8.1 billion of cash, restricted cash and bitcoin, 7.6 billion attributable to Hut 8, is accurate and almost entirely restricted. Of the 7.6 billion, 6.8 billion is project cash that can be spent only on the two campuses and their debt service. The parent's own freely available resources at June 30 were about 500 million in cash and unencumbered bitcoin, which is the number against which overruns and Phase 2 equity must be measured. [1]

Events after June 30

July 2026: Beacon Point Phase 2 lease signed; American Bitcoin's 1-for-15 reverse split. September 24, 2026: 1.07 billion four-year senior secured revolver with JPMorgan as agent and twelve lenders, undrawn at closing. October 14 to 16: on-chain trackers reported about 1,589 BTC moving from Hut 8-linked wallets to exchanges, unconfirmed by the company. [1, 3, 4]

Issuer obligations and recourse

Debt by instrument

Instrument [1, 3, 5, 6]PrincipalTermsRecourse
Hut 8 DC LLC 6.192% senior secured notes due November 15, 2042 (River Bend)3,250.0Issued April 30, 2026 at par, 6.41% effective; interest from November 15, 2026; principal semi-annual from May 15, 2028 to maturity, fully amortizing; make-whole to May 15, 2042; change of control offer; first liens on project assets and accounts, pledge of issuer equity; debt service reserve account; BBB minus at S&P and Fitch; about 95% loan-to-cost with 184 of prior equity returned to the parentNon-recourse. Not guaranteed by Hut 8, the tenant or Google
Beacon Point DC LLC 6.129% senior secured notes due November 30, 2042 (Phase 1)4,250.0Issued June 9, 2026 at par, Treasuries plus 165, 6.27% effective; interest from November 30, 2026; principal semi-annual from May 30, 2030, fully amortizing; make-whole to May 30, 2042; same security package; Baa2 at Moody'sNon-recourse. Not guaranteed by the parent, the tenant or any affiliate
FalconX term loan200.0May 2026, 7.0% fixed, matures April 30, 2027; bitcoin collateral in segregated custody; prepayable after six monthsRecourse limited to the pledged bitcoin
TZRC secured promissory note35.115.25% PIK, due April 8, 2027; secured by Hut 8's 50% interest in the King Mountain joint ventureNon-recourse to Hut 8
Two Prime revolving facility200.0 commitment7.99%, 364 days from first draw; undrawnSubsidiary borrower
JPMorgan senior secured revolver, September 24, 20261,070.0 commitment, letter of credit sublimit equal to the full amountFour years; SOFR plus 1.50% to 2.00% on a consolidated debt to market capitalization grid (1.50% below 0.60x, 1.75% to 1.00x, 2.00% above); 1.75% until the first compliance certificate; secured by pledged equity of material subsidiaries with project entities carved out; incurrence tests at 1.10x to 1.20x debt service coverageParent, secured; undrawn
Coatue 8% convertible note0159.3 of accreted principal converted May 2026 into 9.7 million shares at 16.395Extinguished
Bitmain miner purchase liability371.7American Bitcoin's obligation, settled by forfeiting 3,090 pledged BTC if the redemption option is not exercisedAmerican Bitcoin

Scheduled principal: 2027, 235.1 (FalconX and TZRC); 2028, 86.4; 2029, 100.6; 2030, 238.0; thereafter, 7,075.0. The River Bend amortization of about 346 a year on an annuity basis begins May 2028; Beacon Point's of about 497 a year begins May 2030. There is no refinancing event in the structure before 2042. [1]

The revolver's one covenant

From the quarter ending March 31, 2027, Liquidity, defined as unrestricted cash of the borrower and restricted subsidiaries excluding project entities before their commencement date plus undrawn revolver commitments, may not be less than 40% of commitments (428) before the stabilization date and 25% (267.5) after it. Because undrawn commitments count toward Liquidity, the covenant in practice caps drawings: with the parent at 234 of unrestricted cash, exposure could not exceed about 876 before stabilization and about 1,036 after. The pricing grid is keyed to debt to market capitalization, so a falling stock raises the margin. The revolver is sized for letters of credit, which is how the company has described it; drawn to fund construction equity it becomes corporate debt sitting behind nothing but the equity in two project companies. [3]

How the project structure isolates the parent

Each project company holds its own construction, interest and debt service reserve accounts funded from note proceeds. Rent from the tenant is the sole source of debt service. The parent's claim is the residual equity after a 16-year amortization schedule. Distributions during construction are nil; after commencement they are whatever survives the waterfall and the restricted-payment covenants, which the filing does not quantify. The company says the River Bend notes were sized to leave no incremental equity contribution expected from Hut 8, and that is the point: at 95% loan-to-cost there is also no cushion for the parent to lean on. Any overrun is a parent cash call, and refusing it means a half-built campus with 3.25 billion of debt and a termination clause in the lease. [1, 5]

Contracted revenue and the tenant chain

Campus [1, 5, 6, 7]Tenant and end userCritical IT MWTermBase contract valueExpected average annual NOIDeliveryCredit support
River Bend, St. Francisville, LAFluidstack USA IV Inc.; press reports name Anthropic as the end user, unconfirmed in filings245 (330 utility, Entergy)15 years plus three 5-year options7.0 billion (17.7 with options), 3% escalator454 (6.9 billion over the base term)First hall Q2 2027, remaining halls through 2027Google LLC backstop on rent and pass-throughs for the base term; cap not disclosed; a separate backstop on the operations services agreement expected
Beacon Point Phase 1, Nueces County, TXUnnamed high-investment-grade technology company; secondary sources say AA minus or better; the sell side guesses Meta352 (500 utility, AEP Texas)15 years plus three 5-year options9.8 billion (25.1 with options), 3% escalator655Energization Q1 2027, first hall Q3 2027Tenant covenant only; triple-net, take-or-pay
Beacon Point Phase 2Same tenant352 (500 utility)15 years plus three 5-year options9.8 billion (25.1 with options)655First hall Q2 2028Tenant covenant only; unfinanced
Portfolio94926.6 billionmore than 1.75 billion100% leased to or backstopped by investment-grade counterparties, per the company

Fluidstack holds a right of first offer on up to 1,000 MW of expansion at River Bend, subject to power. The 8,660 MW development pipeline beyond the two campuses carries no leases and no financing. [2, 5]

Two observations. First, concentration: 74% of contracted value sits with one unnamed hyperscaler on one campus, and 26% with Fluidstack through Google. A Fluidstack failure costs Hut 8 nothing while Google performs; a problem at the unnamed tenant has no backstop at all, which is why the market's guess about its identity matters. Second, Hut 8 has delivered 1.3 of colocation revenue and no hosting revenue to date; the 1.75 billion of expected NOI is entirely in the future and entirely dependent on two greenfield construction programs delivering 1,330 MW of utility capacity inside eighteen months.

Free cash flow scenarios and quarterly timing

This is a parent-level sensitivity for Hut 8 Corp.'s own unrestricted cash. It excludes the project accounts, which can only be spent on the campuses, and American Bitcoin, whose cash and bitcoin belong to a 53.6%-owned listed subsidiary. Every line is an analyst assumption; the company has disclosed neither the campus budgets nor the Phase 2 financing plan. Q3 2026 has elapsed but is unreported.

AssumptionDeliveryDelayed deliverySevere
Campus construction cost, both financed phasesAbout 7.9 billion (3.4 River Bend, 4.5 Beacon Point Phase 1), fully funded by notes and reservesSame, plus 550 of overruns funded by the parent across Q4 2026 to Q4 2027Same, plus 1,100 of overruns across Q4 2026 to Q1 2028
Beacon Point Phase 2 cost and equityAbout 4.5 billion at 90% loan-to-cost; 450 of parent equity across Q4 2026 to Q3 2027700 of parent equity, financing at a lower advance rate900, financing at 80% loan-to-cost
Corporate overhead, FalconX and TZRC interest, net of King Mountain distributions20 a quarter3040
FalconX 200 at April 30, 2027Repaid from the sale of about 2,500 of the pledged bitcoin at 80,000SameSame
River Bend distributions after rent commencement30 in Q4 2027, then 60 a quarterNone, delivery slipsNone
Revolver, ATM, further bitcoin salesNoneNoneNone

Delivery case

LineQ3 26Q4 26Q1 27Q2 27Q3 27Q4 27Q1 28Q2 28
Opening parent cash23421414424(146)(316)(306)(266)
Corporate overhead and interest, net(20)(20)(20)(20)(20)(20)(20)(20)
Project cost overruns funded by parent00000000
Beacon Point Phase 2 spend and equity0(50)(100)(150)(150)000
FalconX repayment, net of bitcoin sold00000000
Distributions from River Bend00000306060
Closing parent cash before remedies21414424(146)(316)(306)(266)(226)

Delayed delivery case

LineQ3 26Q4 26Q1 27Q2 27Q3 27Q4 27Q1 28Q2 28
Opening parent cash23420474(156)(486)(816)(1,096)(1,226)
Corporate overhead and interest, net(30)(30)(30)(30)(30)(30)(30)(30)
Project cost overruns funded by parent0(50)(100)(150)(150)(100)00
Beacon Point Phase 2 spend and equity0(50)(100)(150)(150)(150)(100)0
FalconX repayment, net of bitcoin sold00000000
Distributions from River Bend00000000
Closing parent cash before remedies20474(156)(486)(816)(1,096)(1,226)(1,256)

Severe case

LineQ3 26Q4 26Q1 27Q2 27Q3 27Q4 27Q1 28Q2 28
Opening parent cash2341944(336)(776)(1,216)(1,606)(1,896)
Corporate overhead and interest, net(40)(40)(40)(40)(40)(40)(40)(40)
Project cost overruns funded by parent0(100)(200)(250)(250)(200)(100)0
Beacon Point Phase 2 spend and equity0(50)(100)(150)(150)(150)(150)(150)
FalconX repayment, net of bitcoin sold00000000
Distributions from River Bend00000000
Closing parent cash before remedies1944(336)(776)(1,216)(1,606)(1,896)(2,086)

Negative balances are cumulative unfunded requirements before remedies, not feasible cash holdings. The point of the exercise is to size the requirement against the remedies, which for Hut 8 are unusually large relative to the parent's cash.

Remedies and their limits

RemedyCapacityLimit
Unencumbered bitcoin at the parentAbout 4,465 BTC, about 360 at 80,000, before any October salesPrice risk; a sale is a signal the market reads immediately, as the October 14 to 16 wallet movements showed
JPMorgan revolver1,070 commitment; about 640 drawable before stabilization once the liquidity covenant applies, more with higher cashCorporate debt behind project equity; pricing steps up as the stock falls; described by the company as a letter-of-credit facility
Two Prime facility200364-day tenor once drawn, 7.99%
Hut 8 ATM695.7 remaining of 1,00010 million shares at 67.75 is 8% dilution; no sales in Q2
American Bitcoin stake53.6% of a company with about 393 of free bitcoin at 80,000 and a 2.1 billion ATM with 385 usedSelling down the stake deconsolidates the mining business; American Bitcoin's cash is not the parent's
Phase 2 at 95% loan-to-cost, as at River BendCuts the parent equity to about 225Requires the same investment-grade print in a market where the Applied Digital 7% notes trade at 94.5 and JPMorgan has cut the sector's project bonds
Delay Phase 2Removes 450 to 900 of useThe Phase 2 lease has a Q2 2028 delivery date and the tenant has already shown it will double down on the site

The delivery and delayed cases, 316 and 1,256 of peak requirement, are covered by bitcoin, the revolver and the ATM without touching the project companies. The severe case, 2,086, exhausts them and needs equity or a Phase 2 print at the River Bend advance rate. That is the equity thesis in one line: Hut 8's parent has 500 million of its own money and 1.6 billion of committed but conditional liquidity against two campuses with no overrun cushion and a third phase with no financing. [Confidence: Medium]

Project debt service tests

Project [1, 5, 6]NotesCoupon interest a yearFully amortizing debt service a yearExpected average annual NOINOI to interestNOI to debt service
River Bend, amortizing May 2028 to November 20423,2502013464542.26x1.31x
Beacon Point Phase 1, amortizing May 2030 to November 20424,2502604976552.51x1.32x
Both7,5004628431,1092.40x1.32x

Debt service is level-payment annuity arithmetic from the first principal date to maturity at the coupon; the indentures' actual schedules may front- or back-load. The 1.3x coverage after full amortization is consistent with S&P's reported 1.31x minimum for River Bend and is adequate for a BBB minus project bond with an investment-grade payor behind the rent. Until the first hall at each campus commences, interest is paid from the reserves funded at closing, so the first coupons on November 15 and November 30, 2026 carry no information about delivery. The first information arrives when the reserves would have to be topped up, which is the moment a delay becomes a parent cash call. [Confidence: High on the arithmetic]

Recovery and failure transmission

Who absorbs losses first

At the project level, the order is construction reserves, then the debt service reserve, then the parent's completion support if any exists in the indentures (the filing describes none beyond the 5% equity), then the tenant's lease and its backstop, then the collateral. A River Bend tenant failure is Google's problem for the base term; a Beacon Point tenant failure has no backstop, but the tenant is the credit the notes were rated on. At the parent, there are no unsecured term creditors to recover anything: the revolver and Two Prime are secured and undrawn, FalconX and TZRC are limited to their collateral. Parent equity is the residual of two project companies after 16 years of amortization, plus the American Bitcoin stake, King Mountain, bitcoin and land. In a benign case the equity in the two campuses stabilizes at perhaps 1.3 billion of NOI less 843 of debt service, about 450 a year of distributable cash before taxes and Phase 2; in a severe case the parent spends its liquidity on overruns and equity, both campuses deliver late, and the stock, not the debt, carries the loss. [Confidence: Medium]

The most vulnerable links

  1. Overruns at 95% loan-to-cost. River Bend's structure returned equity to the parent rather than leaving it in the project. Every dollar of overrun is a dollar from a parent with 234 of cash. Hyperscale builds of this scale in Louisiana and coastal Texas in 2026 and 2027 compete for the same labor and switchgear as every other name in this file.
  2. Beacon Point Phase 2 financing. 4.5 billion of construction against a lease that starts delivering in Q2 2028, with no print yet. If it prices like River Bend, the parent's equity is about 225; if the project bond market has moved to 80% loan-to-cost, it is about 900. The spread between those two numbers is larger than the parent's cash.
  3. Delivery against the lease. First halls are due Q2 2027 at River Bend and Q3 2027 at Beacon Point, both greenfield, both with substations under construction. Take-or-pay leases carry delivery remedies the company has not disclosed. S&P's project rating assumed the schedule.
  4. Bitcoin as the liquidity reserve. About 360 of the parent's 600 of own liquidity is bitcoin, and American Bitcoin's balance sheet is bitcoin against a Bitmain liability. A fall from 80,000 to 54,000 triggers the FalconX margin call and halves the parent's cushion at the same time.
  5. The unnamed tenant. 74% of contracted value with one counterparty on one campus, no backstop, identity undisclosed. The debt was rated on that name; the equity is a bet on it.

Evidence that would defeat the thesis

A Phase 2 financing at 90% loan-to-cost or better in the first half of 2027; Beacon Point energization confirmed in Q1 2027 and River Bend's first hall delivered in Q2 2027 on budget; the revolver remaining undrawn through the March 31, 2027 covenant test; no bitcoin sales beyond the FalconX repayment; a disclosed tenant identity at Beacon Point. Any three of these leave the equity short with no credit story at all and a company that is, on the company's own numbers, building toward 1.75 billion of investment-grade-leased NOI on 7.5 billion of 6.1% to 6.2% debt.

Protection selection

There is nothing to protect against at the parent. Parent CDS would require a reference obligation and Hut 8 Corp. has none: no bonds, no converts, no drawn loans. The project notes are the only debt, and a short of them is a short of Google or of an AA-rated hyperscaler on a 1.3x-covered amortizing structure trading above par. The expressions that exist are the common stock, which the desk is short at about 5% of NAV from the October 19 open, and American Bitcoin, which is the purer bitcoin and Bitmain-liability instrument. A pair, long the project notes against short the parent equity, would isolate the construction and Phase 2 risk from the tenant credit, but the notes' liquidity and the sector-wide project-bond selloff make the long leg a basis risk of its own. [Confidence: High]

The implication for the book: of the nine names, Hut 8 is the one whose equity short is least connected to the firm's credit thesis. It works if construction slips or Phase 2 does not print; it loses if the company delivers, and the company has so far delivered the leases and the financings it said it would. Sizing it the same as CoreWeave or Core Scientific treats a construction bet as a credit bet.

Research priorities and source register

The decisive statement

Under the delivery assumptions Hut 8's parent requires about 316 of liquidity beyond its cash at the September 2027 trough, covered three times over by bitcoin, the revolver and the ATM. Under the delayed assumptions the requirement is 1,256 by June 2028, still inside identified remedies. Under the severe assumptions it is 2,086 and requires equity or a 95% loan-to-cost Phase 2 print. No parent debt exists for any of this to default on. The debt is investment-grade project paper with a Google backstop or an AA tenant behind it and no maturity before 2042.

Highest priority evidence

Obtain the River Bend and Beacon Point budgets, cost-to-complete and contingency; the indentures' debt service reserve sizes, construction account balances and restricted-payment terms; any parent completion undertaking; the Beacon Point tenant's identity and the lease's delivery remedies; the Google backstop cap and the operations services agreement backstop; the Phase 2 financing structure, advance rate and timing; the revolver's stabilization date definition; the current parent bitcoin count after October's wallet movements; and American Bitcoin's standalone liquidity. The Q3 report in early November should show the first construction-progress disclosure since the notes closed.

Source register

[1] Hut 8 Q2 2026 Form 10-Q, filed August 2026: balance sheet, cash flow statement, Note 5 (digital assets and Bitmain), Note 8 (TZRC), Note 9 (loans and notes), Note 12 (equity and American Bitcoin), MD&A liquidity. https://www.sec.gov/Archives/edgar/data/0001964789/000110465926090025/hut-20260630x10q.htm

[2] Hut 8 Q2 2026 results release, August 4, 2026: 949 MW, 26.6 billion, 1.75 billion of NOI, 8.1 billion of liquidity with 7.6 billion attributable to Hut 8, Phase 2 financing "actively pursuing." https://www.sec.gov/Archives/edgar/data/1964789/000110465926090041/tm2621890d1_ex99-1.htm

[3] Revolving credit agreement, September 24, 2026, Exhibit 10.1: Section 6.09 financial covenant, definitions of Liquidity, Unrestricted Cash Amount, Debt Service Coverage Ratio, Applicable Margin grid, Designated Project Entity carve-outs. https://www.sec.gov/Archives/edgar/data/0001964789/000110465926111154/tm2625691d1_ex10-1.htm

[4] On-chain wallet movements October 14 to 16, 2026, Lookonchain, unconfirmed by the company. https://x.com/lookonchain/status/2110900734141346251

[5] Hut 8 Q1 2026 results release, May 6, 2026: River Bend notes at about 95% loan-to-cost, 184 of equity returned, no incremental equity expected; FalconX refinancing; Coatue conversion. https://www.sec.gov/Archives/edgar/data/0001964789/000110465926055894/hut-20260506xex99d1.htm

[6] Beacon Point Phase 2 lease announcement, July 20, 2026. https://www.sec.gov/Archives/edgar/data/0001964789/000110465926084862/tm2620835d1_ex99-1.htm

[7] River Bend lease announcement: Fluidstack, 245 MW, 7.0 billion, Google backstop on rent and pass-throughs for the base term, ROFO on 1,000 MW, up to 85% loan-to-cost then contemplated. https://www.prnewswire.com/news-releases/hut-8-signs-15-year-245-mw-ai-data-center-lease-at-river-bend-campus-with-total-contract-value-of-7-0-billion-302644600.html

[8] Beacon Point notes rating coverage: Baa2 at Moody's, Treasuries plus 165, tenant rated AA minus or higher per secondary sources; River Bend BBB minus at S&P and Fitch. Agency releases not obtained.

Market indications: River Bend and Beacon Point notes at fair values of 3.30 billion and 4.30 billion at June 30 per the 10-Q, Level 2. Equity 67.75 at the October 16 close, 123.2 million shares. Bitcoin about 80,000 to 82,000 on October 15 per CoinDesk. The Q3 results date is taken from the desk's calendar as November 4 and is unconfirmed.

Calculations are reproducible from the inputs shown. Project debt service uses level annuity arithmetic from the first principal date to maturity at the coupon. Scenario figures are rounded USD millions; precision in arithmetic does not imply precision in forecasting. CDS: credit default swap. NOI: net operating income. ATM: at-the-market equity program. LTC: loan-to-cost. ROFO: right of first offer.

Provided for informational purposes only; not investment advice or an offer or solicitation. Scenario outputs are analyst assumptions, not forecasts of default. Affiliates of Theseus may hold long or short positions, including credit default swaps, in the companies discussed. See Disclaimers.